A19/A182 roadworks
Along with our contractor, BAM Nuttall, we have started works to improve traffic flow and enhance capacity at the A19 / A182 junction, to facilitate commercial development at Jade business park and in the local area.
The improvements will support the expansion of the business park, allowing for the creation of an additional 500,000 sq ft of commercial space and up to 2,000 jobs. These works as well as forthcoming capacity improvements at the Dalton Park Signals will also improve the traffic flow and journey times for general traffic. Improved pedestrian and cyclist connections will be implemented as part of this scheme.
Works that will be completed
The dumbbell roundabouts on each side of the A19 will be removed and converted into signalised junctions, with dedicated crossing facilities for pedestrians and cyclists. The existing number of traffic lanes on the A182 bridge, spanning the A19, will be increased, with widening also occurring on approaches to the junction. A new standalone cycle / footbridge spanning the A19 will also be implemented.
A19/A182 – Highway Improvement Works (PDF) [676KB]
Visualisation of completed scheme
A19/A182 Jade Junction visualisation of completed scheme transcript (PDF) [8KB]
Upcoming programme of works and diversions
Preparatory works have already been undertaken with the scheme programmed for completion early 2025.
Phase | Proposed traffic management | Time | Expected start | Expected end | Diversion and diversion distance |
---|---|---|---|---|---|
A182 westbound lane widening | Lane closures | 24 hour | Mid-March 2024 | Late-June 2024 | |
A182 eastbound lane widening | Lane closures | 24 hour | Early-July 2024 | Mid-August 2024 | |
A19 northbound off slip lane widening | Lane closure | 24 hour | 26 April 2024 | Mid-August 2024 | |
Dalton Park signals improvement works | Lane closures | 8.00pm to 6.00am (night time only) | Mid-April 2024 | Late-August 2024 | |
Spring Road lane widening | Two-way traffic lights | As and when required | 1 July 2024 | 12 July 2024 | |
Footbridge painting | A19 mainline closure
| 24 hour | 29 June 2024 (8.00pm) | 1 July 2024 (6.00am) | From the north: Exit the A19 at the southbound off-slip at Cold Hesledon, rejoining the A19 southbound via the southbound on-slip. From the south: Exit the A19 at the northbound off-slip, continue north on the B1285 and rejoining the A19 northbound via the northbound on-slip. |
Western side of junction -carriageway resurfacing | A19 northbound offslip closure
| 8.00pm -6.00am | 5 August 2024 (8.00pm) | 9 August 2024 (6.00am) | From the south: Proceed north on the A19 exiting at the A1018 northbound, proceeding to Ryhope roundabout, turning onto the B1285 and proceeding south to the Dalton Park signals junction. For those accessing Jade Business Park follow signed diversion along the B1825, Murton and access via Hawthorne Close. Diversion distance 6.5 miles. From the north and east: Proceed south on the A19 exiting at the Easington junction, U-turning at Little Thorpe roundabout. Then heading north on the A19 exiting at the A1018 northbound, proceeding to Ryhope roundabout, turning onto the B1285 and proceeding south to the Dalton Park signals junction. For those accessing Jade Business Park follow signed diversion along the B1825, Murton and access via Hawthorne Close. Diversion distance 12 miles From the west (accessing Seaham): Exit the B1285 onto the A19 northbound, proceeding to Ryhope roundabout, turning onto the B1285 accessing Seaham following the signed diversion route. Diversion distance 6 miles |
Note: Further phases of work are proposed in the vicinity of the A19/A182 junction until scheme completion, anticipated in Spring 2025. Details of future phases will be provided once information is available.
Some diversions for vehicles will be needed during specific construction phases. Localised pedestrian and cyclist diversions will be in place and signposted throughout the various phases of work.
One Network: A19/A182 diversions
Although some disruption is inevitable, we are doing everything possible to minimise the impact to businesses and residents, with phased work and night time closures where possible. Sometimes, the dates of road closures may change due to unforeseen circumstances but we will keep those affected informed.
Funding
The scheme is funded by the Local Growth Fund, Enterprise Zone Fund, Department for Transport, S106 funding and Durham County Council local funding.
![Funded by Uk Government logo](https://durham.gov.uk/image/43787/Funded-by-UK-Government/thumbnail.png?m=1704973865897)
In partnership with
- Funded by Uk Government