February 2023 Update
Pell Frischmann (Design Consultant) VolkerLaser (Specialist Contractor) and Blackett-Ord Conservation (Accredited Conservation Engineers) continue to work together to determine the requirements and preliminary design for the refurbishment of the bridge including updating of the cost estimates. This work is programmed to be complete by the end of February and following a review of the proposals will then progress into a detailed design phase which will allow the programme to be finalised early in 2023 with a view for refurbishments to commence in summer 2023.
We are also currently working with our Contractor to review options for a site compound and working space to help inform the project costings, phasing, and programming. Whilst much of the work will occur using overhead gantries and be retained within the highway corridor, the linear nature of the site means that we will need to utilise an area adjacent the highway for temporary works, material storage, offices etc.